The street lighting project was originally planned in the municipality of Berg. After Berg and the neighbouring municipality of Rohrbach were amalgamated, the renovation project covered the whole street lighting of the former municipality of Berg and a part of Rohrbach. As a result, more lighting points were renovated than initially planned and agreed upon by the municipality and ESCO (139 instead of 121). The municipality’s main aim was to save electricity and use more efficient lighting technology.
Post date: 14 Dic 2016
Type: Caso

The project SOWA Piecewska consisted of refurbishing the public lighting along the street Piecewska in Gdansk (Illuminated area: 19,130 m²). Due to new investments in this district of the city and the installation of a new tram line, an upgrade of the public lighting system was needed.  The project included the replacement of the sodium lamps with LEDs and the modernisation of the infrastructure.The City of Gdańsk obtained a subsidy for this project and the Regional Fund for Environmental Protection covered 45% of the investment.  
Post date: 14 Dic 2016
Type: Caso

With a population slightly below 1,000 inhabitants, the municipality of Cabanillas decided to evaluate an energy efficiency project with its streetlighting. The main objective was the improvement of the physical state and energy efficiency of the streetlight system as well as maintaining or increasing the quality of the service. The municipality was interested in conducting this project with an EPC and an open public tender was published for ESCOs to submit their offers.
Post date: 1 Dic 2016
Type: Caso

The street lighting infrastructure in Kilkenny County was established during the past 60-70 years. The area selected for this project was a representative sample of the 9,800 lamps throughout the county. Street lighting represents approximately 55% of the municipality’s electricity consumption. The light quality was variable and unsatisfactory. The cost of the upgrades was traditionally the barrier to change.
Post date: 22 Nov 2016
Type: Caso

The street lighting system of the municipality of Antiesenhofen was quite old (partly from the 60s) and represented a large percentage of the municipality's electricity consumption. The main objective of the project was to improve the physical state and energy efficiency of the street lighting system without compromising service quality. The municipality was interested in using an EPC (energy performance contracting) model for this project, 4 ESCOs were asked to submit an offer. The municipality wanted to limit the amount of digging and excavation work done during the project.
Post date: 21 Nov 2016
Type: Caso

This supermarket which has approximately 1,200 m2 dedicated to the sales area is located in a residential zone close to the centre of Modena. The building underwent renovation during the summer 2016 before reopening in September. Around 50 workers were onsite per day during the 14 weeks the works lasted. The total requalification cost (supermarket and gallery) was 2.5 M €.  
Post date: 2 Nov 2016
Type: Caso

Construction d’un immeuble de bureau de prestige et réhabilitation d’un bâtiment existant à valeur patrimoniale  
Post date: 17 Ago 2016
Type: Caso

Project type : Extension + refurbishment Building Type : Other building Construction Year : 1920 Delivery year : 2012 Climate zone : [Cfb] Marine Mild Winter, warm summer, no dry season. Net Floor Area : 212 m2  Construction/refurbishment cost : 513,601 € Cost/m2 : 2,423 €/m2   Meuse Energie Nouvelle 2011 Label (New Energy in Meuse) Energy requirements management for historical patrimony buildings by EDF Rubans du patrimoine 2013 LQE 2013 Prize winner (Environmental Quality in Lorraine)  
Post date: 16 Ago 2016
Type: Caso

Ardennes is a solid wood program, built in heart of the island Ardennes street. This 15 unit building with cellar, from one-bedroom to three-bedroom and funded Social Rental Loans (PLS), was designed by the architectural firm Design SF. It finds (...)
Post date: 8 Ago 2016
Type: Caso

The project involves the realization of BMCE Academy, located bouskoura. This project consists of a set of training rooms, a reception center, an amphitheater, a restaurant, a bank branch and finally a Data Center.